Kerry, Good input. The car is already in etching primer from the rockers up and the undercarriage & firewall have been painted the color of the car. ( It's listed in New Cars thread under Mike Workman's 69 Camaro ) Fitting the front sheetmetal now. What I like best about this plan is it allows you to keep moving and also doing different parts of the project through to completion.
I believe I'm going to:
1 Paint all jams / edges, inner fenders, and core support.
2 Install 10 bolt rerend (to roll around) with DSE springs and KYB shocks.
3 Install booster and rest of brake system
4 Install engine, transmission, fuel tank and ect.
5 Spray car
6 Wiring.
7 Install door glass and qrt. glass
8 Interior.
9 Install new 12 bolt rearend
10 Glass
11 Trim69 Camaro w/LS1.
Start date April 2002, completion date June 2013. But it will be well worth it!
-